Home
Hellenic Ministry of Infrastructure and Transport
Jan 14
By admin
Aposelemis Dam, Water Treatment and Water Supply Projects in Northern Crete
The dam is 56 m heigh. It is of rockfill type with an impervious clay core, upstream and downstream rock…
Jan 13
By admin
Design of the Smokovo irrigation network
Designed works include: A main water intake steelpipe is 2500mm, combined with a hydroeletric power…
Jan 12
By admin
Gadouras dam. Water treatment and supply works in Rhodes island
The project includes the Gadoura dam and appurtenant works construction, the water mains to the town of…
Jan 12
By admin
Design of the water supply extension of the Gadouras dam pipelines and water mains to the city of Rhodes
The project involves the extension of the existing pipeline to a wider area, covering potable water…
Jan 12
By admin
Technical Consultant for the preparation of a water supply masterplan for the island of Lesvos
A set of necessary works are suggested, along with water conservation and environmental objective target…
Jan 12
By admin
Environmental flood protection works in urban areas - Adjustment of Xerias stream in Korinthos
Xerias river basin has an area of 174 km2 and extends from the town of Korinthos (North) to the Southern…
Jan 12
By admin
Triantafyllia dam and appurtenant structures design / Technical Consultant for Triantafylia dam works construction
It is a rockfill dam with clay core, 77m high and 560m crest length. The total volume of the dam is 2.…
Jan 12
By admin
Software development for the operation of the National Data Bank of Hydrological & Meteorological Information (NDBHMI - 3rd Phase) using GIS - Publish of the Database
The project comprises of 5 discrete phases: Data entry and processing. Software and equipment supply for…
Jan 12
By admin
Consultant for the Implementation of Feasibility Study and Environmental Studies adjustment for the Acheloos river diversion works to Thessaly plain
Masterplan for the diversion works considering hydrologic data, environmental issues and hydro-power…
Jan 11
By admin
Highway design for the update of the New National Road into a Highway (ΠΑΘΕ), section: Stylida - Raches (Chainage 12+000 - 32+000)
The stormwater and drainage works design of the 180km2 basin refer to : The main highway, 19.235 km long
Jan 11
By admin
Design of Lassithi plateau diversion tunnel to Aposelemis dam and its water supply extension to Agios Nikolaos
Construction of a 90Km long external pipeline from the Aposelemis Dam water treatment plant to Agios…
Jun 13
By admin
Gadouras Dam break analysis and flood wave propagation. Emergency Action Plan
Potential failure mechanisms (overtopping and piping) were considered. 1D and 2D flood wave propagation…